Solicitation required four key personnel that each had "a minimum two years' experience with five years preferred in supervising warehouse logistical operations." But 2 of the protestor's key personnel did not meet the 2-year minimum. Agency considered that a material deficiency and GAO upheld the agency's decision. Protest denied.

GAO: Hurricane Consulting, Inc., B-423839,B-423839.3,B-423839.4,B-423839.5 (Jan 02, 2026)